Construction Process
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process1.jpg
Log packages arrive by truck.
Package is unloaded from truck by Pigeon Creek on job site or nearest possible location.
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process2.jpg
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process3.jpg
Logs are distributed on subfloor.
Wiring holes are drilled in early courses.
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process4.jpg
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process5.jpg
Logs are easily cut and stacked
Log walls are completed and ready for construction of 2nd floor.
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process6.jpg
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process7.jpg
Construction of 2nd floor is quick and easy.
After 2nd floor is complete, dormer or 2nd floor walls are constructed.
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process8.jpg
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process9.jpg
6" x 12" ridge beams and
4" x 8" rafters are set and ready for 1" x 8" tongue and groove.
3 1/2" styrofoam insulation is installed over 1" x 8" tongue and groove.
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process10.jpg
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process11.jpg
OSB or plywood is installed over insulation panels.
Porch beams & rafters are added and roof is constructed.
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process12.jpg
Pigeon Creek Log Company:Pigeon Creek Log Homes Construction Process_files\process13.jpg
Doors and windows are installed and shingles or metal roof make dry in stage complete.